At 08:19 AM 3/29/2003 -0500, you wrote:
I tried using Infolog. I have to create a project first i see. so i
started "projects" and want to create a new project. but it always says i
have to
choose an "activity" before i can create a new project. my activities-list is
empty. what are activities? where do i create them?
thanks
jens
In Projects there is an Activities menu/link. When you click "Activities"
you go to the Activities List page. Click "Add" to make new activities.
Activities are items that occur within a project. For example, I have a
simple project called CS101 and the activities I created for it are CALL
(Make Call to Client), TALK (Receive Call from Client) and VISIT (Meet with
Client). If I remember correctly, before you create projects you have to
create activities and before you create activities you should create
Catagories.
Regards,
Jason
|