Re: [PROPOSAL] Prepare Beam 2.9.0 release


SGTM. Thanks for keeping track of the schedule.

Kenn

On Thu, Nov 15, 2018 at 1:59 PM Chamikara Jayalath <chamikara@xxxxxxxxxx> wrote:
Hi All,

According to the release calendar [1] branch cut date for Beam 2.9.0 release is 11/21/2018. Since previous release branch was cut close to the respective calendar date I'd like to propose cutting release branch for 2.9.0 on 11/21/2018. Next week is Thanksgiving holiday in US and possibly some folks will be out so we can try to produce RC1 on Monday after (11/26/2018). We can attend to current blocker JIRAs [2] in the meantime. 

I'd like to volunteer to perform this release.

WDYT ?

Thanks,
Cham